Puerta America Hotel, Madrid

The Hotel Puerta América, located on Madrid’s Avenida de América, is a landmark high-rise development executed under advanced structural quality control and reinforcement industrialization principles. The building comprises approximately 30,000 m² of gross floor area, distributed over three basement levels dedicated to parking, twelve above-ground floors and a roof level. The structure was entirely constructed in reinforced concrete, incorporating specialized structural solutions designed to optimize the load-bearing capacity of both columns and floor systems

From a reinforcement engineering perspective, the project stands out for the implementation of industrialized reinforcement fabrication and installation processes developed by ERSIGROUP. The central structural core incorporates circular reinforced concrete columns featuring a hollow tubular steel casing embedded within the concrete and supplemented by perimeter-distributed reinforcing bars, significantly enhancing their structural resistance. In addition, several columns were designed as composite elements incorporating internal steel sections combined with reinforcing steel, resulting in high-capacity structural members capable of supporting the building’s demanding load requirements

The floor structure was executed using solid reinforced concrete slabs with thicknesses ranging from 30 cm to 40 cm. Reinforcement was rationalized through the use of custom-manufactured welded unidirectional reinforcement panels, specifically developed to suit the complex geometry of many areas of the building. Special panels measuring up to 12 m in length and 1.20 m in width were fabricated to minimize cutting operations, reduce material waste and accelerate installation activities. The primary reinforcement was arranged at 200 mm spacing, predominantly using Ø12 and Ø16 bars, adapted to the structural requirements of each level

All reinforcing steel was fabricated in ERSIGROUP’s certified industrial production facilities, enabling the application of the Intensive Execution Control Level, one of the highest quality assurance standards established under Spanish structural regulations. The industrialization of reinforcement fabrication and installation significantly reduced construction time, improved assembly quality, minimized steel consumption associated with lap splices and enabled high productivity rates throughout the construction of one of Madrid’s most iconic hotel developments

 

Key Milestones:

  • 30,000 m² hotel development comprising three basement levels, twelve above-ground floors and a roof level
  • Reinforced concrete structural system designed under the Intensive Execution Control Level, one of the highest quality assurance standards under Spanish structural regulations
  • More than 350 guest rooms and suites, together with conference facilities, restaurants, gymnasium and swimming pool
  • Structural solution incorporating circular reinforced concrete columns with embedded hollow tubular steel casings to enhance load-bearing capacity
  • Composite columns combining reinforcing steel and embedded structural steel sections
  • Construction of solid reinforced concrete slabs with thicknesses of 30 cm and 40 cm
  • Use of custom-fabricated welded unidirectional reinforcement panels for slab reinforcement
  • Manufacture of special reinforcement panels measuring up to 12 m in length and 1.20 m in width
  • Reinforcement layouts optimized with 200 mm bar spacing and bar diameters up to Ø16 mm
  • 100% of the reinforcing steel fabricated in ERSIGROUP’s certified industrial facilities
  • Significant reduction in lap splice steel consumption through the use of industrialized reinforcement solutions
  • Improved construction productivity, installation quality and schedule performance through industrialized reinforcement fabrication and preassembly processes developed by ERSIGROUP

    details

    • Categories:
    • Edification
    • Subtype:
    • Hotels
    • Location:
    • Madrid, Spain
    • Customer:
    • Ferrovial Agromán
    • Tn of Steel:
    • 900 Tons