Main features:
The plant will strengthen the hydraulic ring systems of the West Line II, ensuring a 24-hour water supply for a population of more than 235,000 Panamanians.
One of the largest water treatment facilities in the Republic of Panama.
Guaranteed production capacity of 246,000 m³/day (65 MGD), with the possibility of expansion to 322,000 m³/day (85 MGD).
details
- Categories:
- Civil work
- Subtype:
- Hydraulic Work
- Location:
- Colón, Panama
- Customer:
- WATER CONSORTIUM FOR GAMBOA (Constructions Civils Générales S.A. - Water Desalination techniques S.A.)
- Tn of steel:
- 2.500 Tons